Awesome! Thank you!
Hi Chainer / Brass,
There a config switch at: /Program Files/Xerox Freeflow Core/mantisService.exe
The line is <add key="oapJobRetention" value="86400" />
The default value 86400 works out to 24 hours. So if you need to retain the completed jobs for 3 days , you need to set this value to 259200 ( or accordingly) .
Hope this works .!
If I could get this info also that would be great. We have the same issue. Thanks -Brass
I send the information via private message.
Is there a way to change how long a job will stay in the "Completed Jobs" queue?
There's an internal need here for jobs to stay for upwards of three days once they reach the "Completed" state.
Thanks!